
Don’t miss a October 1, 2009 deadline for the state’s UST Petroleum Clean-up Account program
A 'must do' if you have an old UST clean-up
In the summer of 2005, Governor Rell signed into law some time limits to the state's Underground
Storage Tank account program, which provides financial reimbursement for the investigation and
clean-up costs of leaking underground petroleum-storage tanks. The time limits vary according
to the date of the initial application and apply to the initial costs of investigation and clean-up the
so-called Remediation Milestones Nos. 1 through 5 of the program. The first of these deadlines
is coming soon on October 1, 2009, and may represent the last chance for many to apply for
reimbursement for initial costs of clean up.
If your town filed an initial claim for a release to the UST account program before July 1,
2005, you have until October 1, 2009 to submit your supplemental reimbursement applications
for costs to complete Remediation Milestones Nos. 1 through 5. Your supplemental application
must include the completion date or expected completion date of the work, and they must be
submitted within one year of completing the remediation milestone. You must demonstrate that
you've completed another Milestone before you can submit any subsequent reimbursement
applications—although activities for different milestones can be completed and their costs
submitted together. Supplemental applications for costs for Milestones 6 and 7 can still be
submitted after the Oct 1, 2009 deadline.
The law provides an extension beyond October 1, 2009 if your application has not been
reviewed by the UST Petroleum Clean-up Account Review Board within six months of its receipt
by the Clean-up program. Extensions are provided in six-month increments, up to a maximum of
two years. The program acts as financial responsibility coverage under federal law and pays only if
there is no other liability coverage.
If your town filed an initial claim for a leaky UST after July 1, 2005, you have five years to
submit any subsequent reimbursement applications for Remediation Milestones Nos. 1 through 5
for the release. Again, your application must include the date of or the expected completion date
of the work, and it must be submitted within one year of completing the remediation milestone.
Your application must demonstrate that a Milestone has been completed, although activities for
different milestones may be submitted together. You may apply for an extension if your application
has been delayed. Supplemental applications for Milestones 6 and 7 may still be submitted
after these five years have elapsed. Subsequent applications for costs associated with Milestones
6 & 7 may be accepted indefinitely, no matter the date of the initial application, or until the site
meets the state's remediation standards.
To date only 35 municipalities that have underground petroleum storage tanks have applied
to the program; 29 applications have been approved and a total of $6,299,792 has been paid. All
nine local public entities that have applied to the program have been funded, and they've
received a total of $5,802,477 for remediation.
Costs for potable water, contaminated soil remediation, and investigation, and some legal fees
are covered. There are restrictions and limits to the program. Responsible party applicants are
must pay the first $10,000 in costs and there is an overall cap of $1 million per release. The
program acts as financial responsibility coverage under federal law and pays only if there is no
other liability coverage.
The program is budgeted $12 million per fiscal year, which is allocated on a first-come, firstserved
basis with municipalities and non-profits typically receiving expedited reviews from the
Review Board.
If you have questions about the program, please contact Jacques Gilbert, Supervising Environmental
Analyst, Connecticut Department of Environmental Protection. Phone (860) 424-3370.
www.ct.gov/dep.
What are the Remediation Milestones?*
The state uses a "milestone" approach for reimbursement so that costs can be managed
and work can continue uninterrupted throughout an often lengthy remediation
process.
Here is a short description of the seven Connecticut General Statutes Milestones:
- Release response report prepared by an environmental professional, as defined in
C.G.S. section 22a-133v, has been submitted to the Commissioner of Environmental
Protection (describes initial response, initial site investigation, all interim actions, date
of completion of work activities),
- Report describing interim remedial actions taken (describes removal of free product,
provision of potable water, control of soil vapors, date of completion of work),
- Investigation report and remedial actions taken (detailed description of free product
in soil and water, and detailed description of soil and groundwater remediation, cost
estimates, and schedule of work),
- Soil remediation action report (including detailed description of soil pollution, abatement
efforts, documentation of remediation, date of completion),
- Groundwater remedial action (initial) progress report (including detailed description
of remedial actions, results of groundwater monitoring, proposed changes, schedule,
date of completion),
- Annual (continuing) groundwater remedial action progress report (limit of four
responsible party applications per year for costs associated with this milestone for
the release), (includes detailed description of remedial actions, results of groundwater
monitoring, analysis of success of remedial actions, schedule, status, and date of
completion), and
- Final remedial action report (submitted and approved by the Commissioner that
documents the investigation of the release; the remediation of soil water, and air; the
groundwater monitoring, and dates of completion).
* From the www.ct.gov/dep/lib/dep/ustcleanupaccount/milestonefactsheet-final-adobe.pdf
|